Power/Temp Monitor and Control System (EPS/ECLSS) Timeline¶
Date |
Phase |
Status |
29 JAN @ 1200 |
Project inception on ODE |
Completed |
29 JAN @ 1400 |
SEP Step 1: Initial Questions |
Completed |
29 Jan @ 1600 |
SEP Step 2: Requirements Document |
Completed |
29Jan @ 1900 |
SEP Step 3: Block Diagram |
Completed |
30 Jan @ 1700 |
SEP Step 4: Preliminary Design |
Completed |
31 Jan @ 1700 |
SEP Step 6: Detailed Design |
Completed, PCB layout scheduled for 25 FEB 2013 |
01 Feb @ 0800 |
SEP Step 7a: Design Review (filed) |
Completed |
04 Feb @ 1400 |
SEP Step 7b: Design Review (returned) |
- |
04 Feb @ 1500 |
SEP Step 8: Parts ordering |
- |
18 Feb |
SEP Step 9: Assembly |
- |
NA |
SEP Step 10: Integration |
not necessary |
18 Feb |
SEP Step 11: Testing |
begins immediately after assembly is complete and continues until delivery or deployment |
04 Mar @ 0800 |
SEP Step 12: Delivery/Deployment |
- |
15 Mar |
Market solution to other potential clients |
- |
NA |
SEP Step 13: Disposal |
- |