Initial Questions

Version 1 (Jeremy Wright, 01/13/2013 11:36 pm)

1 1 Jeremy Wright
h1. Initial Questions
2 1 Jeremy Wright
3 1 Jeremy Wright
The discussion that led to this set of initial questions can be found "here":https://opendesignengine.net/boards/18/topics/287
4 1 Jeremy Wright
5 1 Jeremy Wright
*Q1. Why are we making this?*
6 1 Jeremy Wright
7 1 Jeremy Wright
Tracking, communication, and command & control of spacecraft are essential capabilities for a spacefaring civilization. Ground stations are the principle links between the spacecraft and Earth used to facilitate these capabilities. The series of ground station related projects will develop the necessary open source hardware to perform these functions.
8 1 Jeremy Wright
9 1 Jeremy Wright
*Q2. Who is this for?*
10 1 Jeremy Wright
11 1 Jeremy Wright
Mach 30 volunteers, Makerspaces and their members, CubeSat designers and operators (including universities). With some minor modifications, most of them software, radio astronomers could be added to the list of users as well.
12 1 Jeremy Wright
13 1 Jeremy Wright
*Q3. How will this be used?*
14 1 Jeremy Wright
15 1 Jeremy Wright
Early ground stations will be used to facilitate voice communications with orbiting satellites (including the ISS, HAM satellites, and CubeSats).  Note, not all satellites will support voice communications, in which case the early ground stations will simply provide a means of listening to the satellites' other radio signals. Data capabilities can be added easily to the system, either by demodulating the audio stream (as in a computer modem), or by using an Software Defined Receiver (SDR) such as the AMSAT Funcube Dongle or USRP and running the demodulation through a software module (GNU radio) using a PC or Laptop.
16 1 Jeremy Wright
17 1 Jeremy Wright
*Q4. What features does it need to have (now)?*
18 1 Jeremy Wright
19 1 Jeremy Wright
Ability to predict opportunities for contact, and the ability to receive and send voice traffic.
20 1 Jeremy Wright
21 1 Jeremy Wright
*Q5. What features does it need to have (later)?*
22 1 Jeremy Wright
23 1 Jeremy Wright
In the future, our ground stations should be able to support sending and receiving command and control data from orbiting spacecraft. For command and control a tracking system would be required since those channels tend to be in a higher frequency range and thus will need a dish. This means that directional antennas and antenna rotator will be required. Additionally, it would be interesting to investigate the possibility of linking multiple ground stations together to provide larger coverage area (imagine if makerspaces across the country, or world, had ground stations linked over the internet so smaller satellite operators could have greater coverage and contact to their satellites). Linking would require standardized equipment with the audio stream being synched by a precision GPS timebase. This will probably be necessary for radio science and video applications as well. For something similar in many ways, have a look at http://www.irlp.net/
24 1 Jeremy Wright
25 1 Jeremy Wright
*Q6. What are the legacy requirements?*
26 1 Jeremy Wright
27 1 Jeremy Wright
Transmitting will require HAM radio licenses (technician level or greater) in the US. Other countries may have other requirements.
28 1 Jeremy Wright
29 1 Jeremy Wright
*Q7. Who's going to build this?*
30 1 Jeremy Wright
31 1 Jeremy Wright
This is a point of discussion, since the current 2013 Mach 30 Annual Plan does not yet have hardware expenses budgeted for this project. This project may be built entirely through volunteer work and funding under the Mach 30 banner though.
32 1 Jeremy Wright
33 1 Jeremy Wright
*Q8. How many do we want to make?*
34 1 Jeremy Wright
35 1 Jeremy Wright
This is a great opportunity to develop a kit which individuals, makerspaces, universities, etc could build and set up. We can kitify the omni antenna, for the starter level project and the Yagi antennas and rotator from later versions.
36 1 Jeremy Wright
37 1 Jeremy Wright
*Q9. What is the budget?*
38 1 Jeremy Wright
39 1 Jeremy Wright
Individual level 1 kites have a budget of approximately $200.  However, this project will clearly have multiple kites, so the over all budget will go much higher.  Current estimates are about 5 kites or about $1000. This budget leaves out the expense of radio(s) and additional equipment to keep the entry level version at a level 1 kite tier.
40 1 Jeremy Wright
41 1 Jeremy Wright
*Q10. What is the timeline?*
42 1 Jeremy Wright
43 1 Jeremy Wright
TBD - again the current 2013 Mach 30 Annual Plan did not budget for this to go into production so quickly (we did not anticipate increased levels of participation coming so quickly). The volunteer timeline for the first prototype unit is intended for use within 2013.
44 1 Jeremy Wright
45 1 Jeremy Wright
*Q11. What waste products will be produced by the manufacture and/or operation of this?*
46 1 Jeremy Wright
47 1 Jeremy Wright
TBD - It is most likely that elements from earlier version will be reused or kept as backups. Any components that wear out, fail, or are damaged must be disposed up according to all federal, state and local guidelines in the US, or as regulations require in other parts of the world.