Timeline
Version 1 (Aaron Harper, 02/02/2013 11:23 pm)
1 | 1 | Aaron Harper | h1. Power/Temp Monitor and Control System (EPS/ECLSS) Timeline |
---|---|---|---|
2 | 1 | Aaron Harper | |
3 | 1 | Aaron Harper | |_.Date|_.Phase|_.Status | |
4 | 1 | Aaron Harper | | 29 JAN @ 1200|Project inception on ODE|Completed | |
5 | 1 | Aaron Harper | | 29 JAN @ 1400|SEP Step 1: Initial Questions|Completed | |
6 | 1 | Aaron Harper | |29 Jan @ 1600|SEP Step 2: Requirements Document|Completed | |
7 | 1 | Aaron Harper | |29Jan @ 1900|SEP Step 3: Block Diagram |Completed | |
8 | 1 | Aaron Harper | |30 Jan @ 1700|SEP Step 4: Preliminary Design |Completed | |
9 | 1 | Aaron Harper | |31 Jan @ 1700|SEP Step 6: Detailed Design |Completed, PCB layout scheduled for 25 FEB 2013 | |
10 | 1 | Aaron Harper | |01 Feb @ 0800|SEP Step 7a: Design Review (filed) |Completed | |
11 | 1 | Aaron Harper | |04 Feb @ 1400|SEP Step 7b: Design Review (returned) |- | |
12 | 1 | Aaron Harper | |04 Feb @ 1500|SEP Step 8: Parts ordering |- | |
13 | 1 | Aaron Harper | |18 Feb|SEP Step 9: Assembly |- | |
14 | 1 | Aaron Harper | |NA|SEP Step 10: Integration |not necessary | |
15 | 1 | Aaron Harper | |18 Feb|SEP Step 11: Testing| begins immediately after assembly is complete and continues until delivery or deployment| |
16 | 1 | Aaron Harper | |04 Mar @ 0800|SEP Step 12: Delivery/Deployment |- | |
17 | 1 | Aaron Harper | |15 Mar| Market solution to other potential clients|- | |
18 | 1 | Aaron Harper | |NA|SEP Step 13: Disposal|- | |