h1. Testing v1.0 {{toc}} The testing was done in three main phases, with the first two progressing in parallel: # The mechanical system was tested as a stand-alone unit. # The Data Acquisition (DAQ) system was tested as a stand-alone unit. # The mechanical and DAQ systems were integrated and then tested. h2. Mechanical System Testing h2. DAQ System Testing h2. Integrated Testing