The requirements list matches up to the Initial Questions in step one of the Systems Engineering process as shown below. Each requirement is labeled with FHPR (Far Horizons Project Requirement), followed by the number of the [[Initial_Questions_v1_0|initial question]] that the requirement corresponds to, followed by a dot and then the ID number of the requirement.
8 2 J. Simmons
9 2 J. Simmons
* *FHPR 1.x* - Why are we making this?
10 2 J. Simmons
* *FHPR 2.x* - Who is this for?
11 2 J. Simmons
* *FHPR 3.x* - How will this be used?
12 2 J. Simmons
* *FHPR 4.x* - What features does it need to have (now)?
13 2 J. Simmons
* *FHPR 5.x* - What features does it need to have (later)?
14 2 J. Simmons
* *FHPR 6.x* - What are the legacy requirements?
15 2 J. Simmons
* *FHPR 7.x* - Who's going to build this?
16 2 J. Simmons
* *FHPR 8.x* - How many do we want to make?
17 2 J. Simmons
* *FHPR 9.x* - What is the budget?
18 2 J. Simmons
* *FHPR 10.x* - What is the timeline?
19 2 J. Simmons
* *FHPR 11.x* - What waste products will be produced by the manufacture and/or operation of this?
20 2 J. Simmons
21 2 J. Simmons
22 2 J. Simmons
h3. Technical Requirements
23 2 J. Simmons
24 2 J. Simmons
Technical requirements are those requirements which include measurable performance values.  Each technical requirement should be verified through testing to ensure the design meets the requirement.
25 2 J. Simmons
26 2 J. Simmons
* *FHPR 3.1* The HAB must be able to carry scientific and engineering payloads to a "near space environment" and return the payloads safely.
27 2 J. Simmons
** *FHPR 3.1.1* Individual payload modules must weigh 6 lbs or less.
28 2 J. Simmons
** *FHPR 3.1.2* Total launch weight must be 12 lbs or less.  
29 2 J. Simmons
* *FHPR 3.2* The HAB must be able to withstand the near space environment (*TBD - fill in min temperatures, pressures, and max radiation levels as sub-requirements*).
30 2 J. Simmons
31 3 J. Simmons
* *FHPR 4.1* The HAB will carry payloads to altitudes between 90 kft and 100 kft.
32 1 Jeremy Wright
33 3 J. Simmons
* *FHPR 6.1* The design and operation of the HAB shall comply with "FAR 101":http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&rgn=div5&view=text&node=14:2.0.1.3.15&idno=14#14:2.0.1.3.15.4.
34 3 J. Simmons
35 2 J. Simmons
h3. Project Requirements
36 2 J. Simmons
37 1 Jeremy Wright
Project requirements are the remaining requirements which are not tied to specific performance values.
38 2 J. Simmons
39 2 J. Simmons
* *FHPR 2.1* The HAB must be well documented so as to meet the needs of open source spaceflight designers who will design and build High Altitude Balloons (at Adler and elsewhere).
40 3 J. Simmons
* *FHPR 2.2* The HAB documentation and procedures must be complete enough that Adler operators, students and educators who want to bring near space missions into the classroom, and anyone else interested in running near space missions.
41 3 J. Simmons
* *FHPR 2.3* The HAB documentation must cover the the development, setup, launch, and recovery of the HAB.
42 2 J. Simmons
43 3 J. Simmons
* *FHPR 4.2* The HAB documentation shall include safety guidelines for launch and recovery.  
44 3 J. Simmons
* *FHPR 4.3* The HAB will broadcast a tracking signal to facilitate recovery.
45 3 J. Simmons
* *FHPR 4.4* The HAB will include a parachute or similar descent control system to provide a soft landing.
46 2 J. Simmons
47 5 J. Simmons
* *FHPR 7.1* All HAB design documentation must be open and complete enough so that ANYONE, without necessarily a technical education in high altitude ballooning or engineering, would be able to build and operate the HAB.
48 1 Jeremy Wright
49 5 J. Simmons
* *FHPR 9.1* The cost of the first third-party operational HAB must not exceed $300 excluding "consumables" and tools.
50 2 J. Simmons
51 5 J. Simmons
* *FHPR 10.1* If at all possible, the first third-party HAB should be completed and launched by July 14, 2012.
52 2 J. Simmons
53 5 J. Simmons
* *FHPR 11.1* Electronic waste items, including batteries (lithium and others) and circuit boards, must be disposed of according to all local, state, and federal guidelines.
54 5 J. Simmons
* *FHPR 11.2* If the structures of the HAB are damaged beyond repair during operation, proper disposal/recycling guidelines must be followed for the materials used in its construction.
55 5 J. Simmons
* *FHPR 11.3* Wherever possible, the HAB design should make it as easy as possible to replace components which are consumable or relatively easy to damage.
56 2 J. Simmons
57 2 J. Simmons
h3. Future V2.0 Requirements
58 2 J. Simmons
59 2 J. Simmons
These are for reference only so that future features can be accommodated in the current design where practical.
60 2 J. Simmons
61 4 J. Simmons
Version 2.0 and beyond:
62 4 J. Simmons
* *FHPR 5.1* Controlled descent system (guided landings using parafoil kite to either hit or avoid landing sites)
63 4 J. Simmons
* *FHPR 5.2* Live two-way telemetry (or command & control) and the ability to receive live experiment and operations data
64 4 J. Simmons
* *FHPR 5.3* Stabilized platform system (Adler is making progress on this one)
65 4 J. Simmons
* *FHPR 5.4* Alternative balloon configurations (zero-pressure, super-pressure balloons)
66 4 J. Simmons
* *FHPR 5.5* Alternate lift gasses (Adler uses helium right now)
67 4 J. Simmons
* *FHPR 5.6* A structure to hold the balloon during filling operations and to automatically stop the filling operation for the desired lift
68 2 J. Simmons
69 2 J. Simmons
h3. Glossary
70 2 J. Simmons
71 2 J. Simmons
FHPR - Far Horizons Project Requirement
72 2 J. Simmons
HAB - High Altitude Balloon