Operating Manual

The items below have been gleaned from meeting notes and video obtained during the Far Horizons design meetings and launch.

TODO: These need to be put in the correct order and formed into a proper set of procedures. A format for the procedures needs to be decided on for this page.

Equipment Checklist

ODT (Open Document Text) and PDF versions of this checklist are available.

1.0 Pre-Departure Operations

These are operations that are completed before the launch and chase teams leave for the launch site.

FHPOM 1.1 Break personnel up into teams based on experience and interests, but make sure to have a minimum amount of people on each setup task.
FHPOM 1.2 Make sure that your balloons are not up against anything that might damage them in your equipment transport bag.
FHPOM 1.3 Once you have ensured that all of the equipment is in the transport bag, secure it with zip ties or some other method to keep someone from removing items.

2.0 Setup Operations

FHPOM 2.1 Set up a workspace by laying out the ground tarp and ensuring that it is clean and free of debris, oils, etc. “Clean is key”.
FHPOM 2.2 Lay the helium tanks on one side of the tarp to help keep it from blowing away.
FHPOM 2.3 Remove the safety cover from the helium tank(s).
FHPOM 2.4 Attach the custom built fill connector’s regulator to the first helium tank.
FHPOM 2.5 Use a crescent wrench to tighten (snug) the regulator’s connector to the tank’s valve.
FHPOM 2.6 All personnel who help steady the balloon should wear cotton gloves to help protect the balloon.

Launch Operations

Chase and Recovery Operations